Concrete Delivery Planning

A correct volume estimate still needs a workable order and delivery plan.

Ask about the minimum order

Ready-mix suppliers may set minimum delivery quantities or charge a fee below a threshold. The amount varies by supplier and region. Use the main calculator’s optional small-load threshold as a reminder to ask, not as a promise that a fee will apply.

Advertisements

Confirm truck size and access

Truck capacity depends on the fleet and local rules. Enter the capacity quoted by your supplier to estimate how many truckloads the order volume would require. Confirm access width, ground condition, unloading time and whether a pump or wheelbarrow route is needed. The calculator does not assess site access or truck weight limits.

Do not guess pickup capacity

Dry bag weight equals bag count multiplied by bag weight. Divide it by the payload available for concrete bags to see a minimum trip count. Use your vehicle’s actual payload label and subtract passengers, tools and other cargo. The calculated count is a planning minimum, not permission to exceed a vehicle rating.

Example

A 1.36 yd³ order fits within a supplier-stated 10 yd³ truck capacity, though the supplier may still charge for a small load. If the alternative is 62 bags of 80 lb mix, the dry bag weight is 4,960 lb. At 1,200 lb of available payload after other cargo, at least five trips would be needed. Recheck the quantity and payload before travel.

Final checklist

Confirm the pour dimensions, order increment, truck capacity, minimum load, access, quoted fees, placement time and contingency plan. Use the full ordering checklist before placing the order.

Access sketch for the supplier

Mark the driveway width, turning area, overhead obstacles and approximate distance from the safe truck position to the forms. Include gates, soft ground and slope. Give the supplier this sketch with the requested volume. A delivery quote is meaningful only when the supplier knows whether direct discharge is realistic or a wheelbarrow or pump route is needed.

Small-load comparison

For 1.25 yd³ at $180/yd³, base material is $225. A $250 short-load fee and $175 delivery charge would bring the subtotal to $650 before tax. Another supplier with a higher per-yard price but smaller fixed fees could be cheaper. Ask each supplier for the same quantity, mix and delivery window; do not compare unit rates alone.

A narrow-site example

Imagine a 14 × 18 ft patio at 4 in. Exact volume is 84 ft³ or 3.11 yd³, and 10% extra makes 3.42 yd³ before supplier rounding. The form is behind a narrow gate, 80 ft from the driveway. The volume calculation is unchanged by the gate, but the delivery method, labor and possibly pump cost are not. Tell the supplier about the gate width, route surface, turning area and distance to the form before accepting a material-only price.

A small order example

A 10 × 10 ft slab at 4 in needs 1.23 yd³ exact or 1.36 yd³ with 10% extra. A supplier may have a minimum-load charge or may round the order to a fixed increment. At $180/yd³, 1.5 yd³ of material is $270; a $250 short-load fee and $175 delivery would bring the subtotal to $695 before tax. Another supplier may structure fees differently. Ask for the complete delivered total and how much concrete will actually be billed.

Useful questions

What is the minimum order and increment? How close can the truck safely discharge? Are there weight, height, width or ground-condition limits on the route? Is a pump or additional handling needed? What is the delivery window and waiting-time policy? Who will be on site to direct placement? Write these answers next to the calculated volume.

Questions before you decide

Does truck capacity determine my order?

No. Order from the measured fill plus an explicit allowance, then ask how the supplier will deliver it. Truck size, minimum load and order increment are supplier constraints. Do not inflate a quantity just to match an assumed truck capacity without discussing the quote.

What if the truck cannot reach the forms?

Tell the supplier how far the safe discharge position is from the forms and describe width, slope and ground conditions. Additional handling or pumping may be needed. Keep those costs separate from the per-yard concrete price.

When should access be checked?

Before booking a delivery window, ideally when forms and the base are ready. A sketch and photos may help the supplier assess the route, but follow their instructions. Recheck the route after rain or site changes that could affect ground conditions.

Quote call script

Tell the supplier the intended mix, your exact and waste-adjusted volume, desired order increment, address and proposed delivery window. Describe the safest truck stopping point, gate width, overhead obstructions, distance to forms and ground conditions. Then ask for the billed quantity, per-yard rate, delivery, short-load, waiting and pump charges. Repeat the quoted total back and request it in writing. This sequence keeps the order discussion focused on facts the supplier can price rather than a generic online estimate.

A second delivery scenario

Suppose two separate pours each require 1.4 yd³ with allowance. If they can be placed from one order on the same day with the same mix, a combined 2.8 yd³ request may be priced differently from two small deliveries. But the crew must be able to place both areas within the supplier’s delivery and workability constraints. If pours require different dates or mixes, combine neither the schedule nor the quote simply to avoid a fee. Measure each area separately and discuss the practical sequence with the supplier.

Confirm the last 50 feet

The distance between a safe truck position and the form can be the most important part of delivery planning. Walk that route with the intended crew before booking. Note stairs, narrow turns, fresh landscaping, soft soil and elevation changes. A wheelbarrow route that looks short on a map may be slow or unsafe with a heavy load. Ask the supplier whether direct discharge, a chute, a pump or another approved method is appropriate. Confirm who provides any extra equipment and whether its cost is included. Keep this access decision next to the volume and delivery window in the written order.

Content and calculator by pourmeasure. Formula and assumption notes: methodology and sources. Updated October 2026. No independent engineering review is claimed.