Concrete footing calculator
Estimate the material for a rectangular footing or trench from its finished dimensions.
Enter footing dimensions
Footing volume formula
Length × width × depth gives cubic feet when all three dimensions are in feet. Divide depth in inches by 12 first, then divide cubic feet by 27 to get cubic yards. For several identical footings, multiply by quantity.
Formula: length ft × width ft × (depth in ÷ 12) × quantity ÷ 27 = exact yd³.
Worked example: 20 ft long, 2 ft wide, 12 in deep
20 × 2 × 1 = 40 ft³, or 1.48 yd³ exact. With 10% extra, plan for 44 ft³ or 1.63 yd³. At 0.60 ft³ per 80 lb bag, this would take 74 bags. A supplier may have a minimum delivery quantity.
Measure the excavation you will actually fill
Over-excavation, uneven sides and changes in depth increase volume. Measure the finished trench, not only the drawing. Structural footing dimensions and reinforcement depend on site conditions and local requirements; the calculator does not design them.
Questions people ask
Is this for round piers?
This page is for rectangular footings. Use the multi-pour calculator and choose “Round column / hole” for cylindrical piers.
Why is the order amount larger than exact volume?
The order result applies the extra percentage you entered. It is separate from the geometric volume.
Second example: separate footing runs
Suppose a project has a 24 ft run that is 18 in wide and 10 in deep, plus a 12 ft run that is 24 in wide and 12 in deep. The first run is 24 × 1.5 × 10/12 = 30 ft³; the second is 12 × 2 × 1 = 24 ft³. Together they need 54 ft³, or 2.00 yd³ before allowance. With 10% extra the planning quantity is 2.20 yd³. Calculate different cross-sections separately, then add them.
Do not average the widths or depths of unequal runs unless you first weight them by length. A short deep section can matter more than a long shallow one. The multi-pour calculator lets you keep separate measurements visible when checking an order.
Common footing measurement errors
Use the concrete fill dimensions, not the outer dimensions of a form board. If a trench steps down or widens around a column, break it into non-overlapping volumes. Overlapping rectangles double-count concrete; omitted widened portions undercount it.
The calculator does not determine safe footing size, frost depth, bearing capacity, reinforcement or inspections. Those come from approved plans, local requirements and qualified project advice. A volume estimate should be checked against the drawing before it becomes a purchase order.
Read before you order
Take one final trench measurement
Trenches can widen or deepen after an early estimate because of excavation conditions. Recheck the dimensions you will actually fill before ordering, especially at corners and stepped levels. A 20 ft run that widens from 2 to 2.25 ft at 12 in depth gains 5 ft³, about 0.19 yd³. That can be more than a small rounding difference. Record each run separately if widths vary and compare it with the approved design.
Review changing trench geometry
A footing with a step in elevation needs at least two measured segments when the concrete depth changes. Mark the start and end of each segment on a plan and confirm that the shared boundary is not counted twice. If a column pad or pier intersects the footing, identify the actual filled shape rather than summing two gross rectangles. This is a quantity review only: footing width, depth, reinforcement and bearing requirements remain matters for the approved design and local conditions.