Concrete slab calculator
Enter the finished length, width and thickness. See exactly how the slab volume turns into cubic yards and bags.
Enter slab dimensions
How to calculate concrete for a slab
Multiply length × width × thickness, using the same unit for every dimension. When length and width are in feet and thickness is in inches, divide thickness by 12 to get feet. Divide cubic feet by 27 for cubic yards. Multiply by the number of identical slabs, then apply your chosen waste percentage.
Formula: (length in ft × width in ft × thickness in ÷ 12 × quantity) ÷ 27 = exact yd³.
Worked example: a 10 × 10 ft slab, 4 in thick
10 × 10 × (4 ÷ 12) = 33.33 ft³. That is 1.235 yd³ before extra. With 10% waste, the order estimate is 1.358 yd³, displayed as 1.36 yd³. At 0.60 ft³ per 80 lb bag, 36.67 ÷ 0.60 = 61.11, so round up to 62 bags.
Common square slab sizes at 4 inches
These are material quantities for one rectangular slab, using 10% extra and an example 0.60 ft³ yield per 80 lb bag. Confirm the finished dimensions and your chosen bag label.
| Slab size | Thickness | Exact | With 10% extra | Bags |
|---|---|---|---|---|
| 8 × 8 ft | 4 in | 0.79 yd³ | 0.87 yd³ | 40 × 80 lb |
| 10 × 10 ft | 4 in | 1.23 yd³ | 1.36 yd³ | 62 × 80 lb |
| 12 × 12 ft | 4 in | 1.78 yd³ | 1.96 yd³ | 88 × 80 lb |
| 20 × 20 ft | 4 in | 4.94 yd³ | 5.43 yd³ | 245 × 80 lb |
| 24 × 24 ft | 4 in | 7.11 yd³ | 7.82 yd³ | 352 × 80 lb |
How much for a 10 × 10 ft slab?
At 4 in: 1.23 yd³ exact, 1.36 yd³ with 10% extra. At 5 in: 1.54 yd³ exact, 1.70 yd³ with 10% extra. At 6 in: 1.85 yd³ exact, 2.04 yd³ with 10% extra. These are quantity comparisons, not thickness recommendations.
What this estimate does not decide
This is a material volume estimate. It does not determine structural thickness, reinforcement, ground preparation, joint spacing, delivery minimums or finishing labor. Use the finished pour dimensions and ask a qualified professional about structural design.
Questions people ask
How many yards are in a 10 × 10 slab at 4 inches?
About 1.23 yd³ exact, or 1.36 yd³ with 10% extra.
Can I add multiple slabs?
Use the number-of-slabs field for identical slabs. For different sizes, use the multi-pour calculator.
Thickness changes quantity quickly
A 12 × 16 ft rectangle contains 192 ft². At 4 in thick its exact volume is 64 ft³, or 2.37 yd³; at 5 in it is 80 ft³, or 2.96 yd³. The extra inch adds 16 ft³, about 0.59 yd³, before any allowance. This comparison helps budget alternatives, but the correct design thickness must come from the intended load, subbase, plans and local requirements.
Measure the finished thickness at representative locations. Excavation depth is not automatically concrete thickness because the base layer may occupy part of it. A thickened perimeter should be measured as an additional non-overlapping volume rather than applying the thicker edge depth to the entire pad.
Avoid double-counting slab features
A rectangular slab with a separate strip footing can be estimated as two pours when their volumes do not overlap. If the edge is monolithic, calculate the full slab first and add only the extra depth below that slab at the edge. Multiplying the whole outline by total edge depth would overestimate.
Joints and reinforcement affect construction planning but usually do not justify subtracting meaningful concrete volume from a small estimate. Openings, pits and large blockouts can be measured separately. Keep a written list of what was included so a supplier or contractor can follow the arithmetic.
Read before you order
Planning slab thickness · Measuring irregular areas · Curing and weather planning
Content and calculator by pourmeasure. Formula and assumption notes: methodology and sources. Updated October 2026. No independent engineering review is claimed.